🏢 Project Details
Project Name:YIIRS SCHOOL PROJECT
Location:Karimnagar, Telangana
Client:YIIRS Projects
Project Mgr:Er. V. Kokkiligadda
📄 Contract Details
Contract Type:LUMP SUM
Contract Value:₹ 5,79,60,000
Start Date:01-Jan-2025
Planned End:31-Dec-2026
☀ Weather Today
36°C
Sunny / Clear
Min 24°C | Max 36°C
⚡ Project Health Score 87% GOOD
87%
■ 90-100: EXCELLENT
■ 70-89: GOOD
■ 50-69: ATTENTION
■ < 50: CRITICAL
📈 Overall Progress
42.35%
% OF WORK DONE
₹ Work Done Value
₹ 2,45,49,460
(CUMULATIVE)
📃 RA Bills Raised
₹ 2,10,75,000
(CUMULATIVE)
💰 Bills Received
₹ 1,58,25,000
(CUMULATIVE)
⚖ Balance Receivable
₹ 52,50,000
(BALANCE)
👥 Total Labour & Safety
57
NOS TODAY (LIVE)
98%
SAFETY
PROJECT PROGRESS SUMMARY 10 Major Stages
S.No Work Description Plan % Act % Var % Status
1Excavation100.00%100.00%0.00%✔ Done
2Foundation100.00%100.00%0.00%✔ Done
3RCC (Columns, Beams, Slabs)60.00%45.60%-14.40%⚡ Prog
4Brick Work50.00%25.20%-24.80%⚡ Prog
5Plastering30.00%10.50%-19.50%⚡ Prog
6Flooring20.00%5.20%-14.80%⚡ Prog
7Electrical Works15.00%4.00%-11.00%⚡ Prog
8Plumbing Works15.00%3.20%-11.80%⚡ Prog
9Finishing Works10.00%0.00%-10.00%⏳ Pend
10External Works10.00%0.00%-10.00%⏳ Pend
OVERALL STATUS 42.35% 29.77% -12.58% Behind
Labour Trend (Last 6 Days) [Black: Planned, Orange: Actual]
19-M
20-M
21-M
22-M
24-M
Today
Weekly Progress vs Target
Planned Target: 42.35%42%
Actual Progress: 29.77%30%
Billing Realization: 75.08%75%
MATERIAL CONSUMPTION (MT / CUM)
MaterialToday (Live)MonthTotal
Cement (Bags)4208,95032,680
Steel (MT)2.8048.60188.40
Sand (Cum)18.00312.001,152.00
Aggregate (Cum)24.00415.001,565.00
RMC (Cum)150.00560.002,250.00
MACHINERY STATUS
EquipmentWorkingBreakdownTotal
Transit Mixers617
Pumps101
JCB101
Vibrators404
Tower Crane101
✔ TODAY'S WORK SUMMARY
✔ RCC work Block B - 2nd Flr
✔ Brick work Block A - 1st Flr
✔ Plastering Block A - Ground Flr
➤ TOMORROW PLAN
➤ Continue RCC Block B
➤ Continue Brick work Block A
⚠ PENDING ISSUES
● Steel supply delay Block B
● Design approval pending
🛡 SAFETY TODAY
✔ Toolbox Talk Done
✔ PPE Compliance 100%
✔ Zero Accidents Reported
LAST SUBMITTED BY:Munna
CHECKED BY:Project Manager
APPROVED BY:Managing Director
Yahweh Constructions

📝 SITE ENGINEER DAILY DPR ENTRY

ONLINE FIELD ENTRY
📋 1. General Site Details
👥 2. Labour Deployment (Today)
🧱 3. Material Consumed Today
🛠 4. Progress, Issues & Tomorrow Plan